7-Storey Ramp Up Warehouse at Pioneer Road
Project Status: Completed
Project Type: Commercial
Share this project:
Location
Pioneer Road, Singapore
Links supplied as prefabricated cages resulted in 100% productivity improvement.
Project Requirements:
Location
Pioneer Road, Singapore
To install this warehouse post-tensioned slab system with drop panel, we supplied the required links in the form of prefabricated cages.
Technical specifications: Average of 400 x T10 shear links per 4.2m x 4.2m drop panel; Total weight of links for each panel: 250 kg
Installation time using non-prefabricated methods: 12 manhours per panel
Installation time taken using BRC’s prefabrication solutions: 6 manhours per panel
6 hours
Total time saved
As a result, workers only needed half the time (6 manhours) that would have been required of conventional link tying (12 manhours) to complete placing the cages for each drop panel.